fbpx

09.09.2024 — Elite Family Residence — Finishing of the south and west facade, connection of water supply system, installation of reducers, installation of metal railings, tying of fire pump, digging of trench for sewerage is in progress. On the ground floor, finishing of walls and installation of plasterboard rails for ceilings is in progress. On the first floor electrical work is being carried out (wiring, continuity testing). The walls of the bathroom are being finished in the mockup.