fbpx

25.09.2024 — Wyndham Grand Residences Batumi Gonio. Villas — Villa 9: construction of the floor slab formwork. Villa 12: reinforcement of the bottom of the foundation. Villas 15-16: formwork for the foundation under-concrete and geodetic work. Geodetic surveying of the formwork is also in progress: columns (villas 3, 5), foundation walls (villas 11, 13), floor slabs (villas 6-9). Dismantling of the fence foundation formwork, reinforcement of the fence foundation wall, geodetic work on the fence wall contouring is in progress.