28.05.25

Elite Family Residence

1. Facade work.
— Puttying the joints of decorative figures.
— Painting of terraces and decorative elements.

2. Installation of interior doors.

3. Electrical installation works.
Installation of finishing electrics in the units.

4. Facing of the entrance group with natural stone.

5. Installation of plasterboard frame.
Works on the -1 floor in the common areas.

28.05.25

Wyndham Grand Batumi Gonio. Villas.

1. Masonry works.
Ceramoblock masonry exterior walls, villa 14.

2. Installation of fireplaces, villa 8.
Fireplace chimney masonry.

3. Work on dismantling of floor slab formwork, villa 14
Removal of formwork after concrete hardening to complete the structure and prepare for the next stage of construction.

28.05.25

Wyndham Grand Batumi Gonio. Riviera.

1. Block A, E. Facade works.
— Facade insulation, installation of mineral wool.
— Installation of soffits.

2. Block A. Masonry works.
Ceramoblock masonry, technical floor.

3. Block A. Plastering works.
Plastering of columns.

28.05.25

Wyndham Grand Batumi Gonio. Family Club.

Block A
1. Facade works.
Facade insulation, installation of mineral wool.

2. Plastering works.
Plastering of the walls of the 2nd floor.

3. Work on the device of ceilings on the balconies.

4. Elevator shafts
Dismantling of formwork beams elevator shafts.

5. Arrangement of screed on the balconies.

28.05.25

Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Electricity supply system installation, 19th floor.
— Plumbing works, 20th floor.

2. Installation of gypsum plasterboard framework.
Closing of columns, ceilings on balconies.

3. Reinforcement of beams, 2–9 floors.

4. Work on the floor screed.
On the 5th floor.

5. Plastering works.
Plastering on the balconies.

6. Arrangement of mocap, 3rd floor.
Finishing works.

27.05.25

Elite Family Residence

1. finishing works.
— Laying of porcelain tiles.
— Installation of moldings.

2. Facade works.
Painting of terraces and decorative elements on the facade.

3. Plumbing works.
Installation of plumbing in the units.

4. electrical works.
Installation of finishing electrics in the units.

5. Installation of interior doors.

6. Facing of the entrance group with natural stone.