03.06.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — On the 2nd floor of Block A, ceramic block walling continues. In Block B, the formwork for the 2nd floor columns is being assembled. In Block C, the installation of retaining wall formwork has started. Reinforcement of staircases is being carried out in the infrastructure building.