fbpx

Wyndham Grand Batumi Gonio. Aqua — On the 2nd floor, installation of GKL partition walls continues. On the 3rd floor the installation of plumbing in mockup is in progress. On the 13th floor the painting of balconies in mockup is in progress. On the 14th floor works on reinforcement of masonry partitions of ceramic block are carried out. On the floors go: – installation of formwork and framing of reinforced concrete sides of balconies – installation of decorative boxes on the balconies – installation of stained glass – dustless ceilings – anti-corrosion work (metal painting) – diamond drilling of engineering holes On the territory are made geodesic work. The lifting of double-glazed windows on the floors is carried out.