fbpx

Wyndham Grand Batumi Gonio. Aqua — Installation of formwork and framing of reinforced concrete sides of balconies continues on the floors. Works on installation of GKL partition walls on the 2nd floor continue. On the 13th floor balconies are being painted in mockup, and on the 3rd floor plumbing is being installed in mockup. Installation of decorative boxes on balconies and installation of stained glass windows is in progress. Installation of the entrance group is in progress. Dusting of ceilings and anti-corrosion works are also in progress. Geodetic works and lifting of double-glazed windows to the floors are in progress. Diamond drilling of engineering holes and installation of lift shaft coverings are being carried out.