Wyndham Grand Batumi Gonio. Riviera — Block A Plastering of ventilation duct shafts is in progress. Block B On the 2nd floor walls are being laid with ceramic block and fireplaces are being laid. The underlayment of supporting edges for stained glass windows is in progress. On the 3rd floor also continues masonry walls with ceramic block. Work on dismantling and installation of staircase formwork is in progress. Block C On the 1st floor continues masonry walls ceramic block. Dismantling of formwork is being carried out on the 2nd floor.