06.03.2024 — Wyndham Grand Residences Batumi Gonio. Family Club — In Block A, the installation of the 5th floor slab formwork continues. In Block B, the formwork for the 3rd stage of the basement wall and the formwork for the floor slab at 0.00 is being assembled.