fbpx

Wyndham Grand Batumi Gonio. Aqua — Installation of stained glass windows and preparation of their hydro/vapour barrier continues at the site. Installation of decorative boxes on balconies, dusting of ceilings, geodesic works, anti-corrosion works (metal painting), lifting of building materials to the floors, arrangement of lift shaft coverings (preparation for installation of lift equipment), diamond drilling of engineering holes, plastering of openings. On the 20th floor the installation of plasterboard frame of internal partitions is in progress.