fbpx

10.06.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — In block A on the 2nd floor the walls are being laid with ceramic block. In Block B, the floor slab formwork is being assembled. In block C, concreting of the retaining wall took place. In the infrastructure building, the floor slab is being concreted.