11.12.2023 — Wyndham Grand Residences Batumi Gonio. Riviera — Block A In the 1st half works on installation of formwork of the floor slab of the 3rd floor are in progress, in the 2nd half reinforcement of the floor slab of the 3rd floor is carried out. Block B Excavation works are in progress. Block E Preparation for laying ceramic block parapet on the roof.