17.09.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — In Block A, fireplaces are being laid, the monolith of the staircases is being poured and the formwork on the terrace is being installed. In Block B – monolith pouring of the parapet top, monolith pouring along the parapet, laying of ceramic block (first floor), laying of fireplaces and concreting of staircases. In Block C – pouring of slab monolith and construction of fences.