18.04.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — In Block A, the masonry of walls with ceramic block continues. In Block B, concreting of vertical structures has been completed, reinforcement of the foundation slab is underway, and the retaining wall formwork is being installed. Concreting of the foundation preparation has been completed in Block C. Waterproofing of the foundation of the infrastructure building is underway.