fbpx

22.12.2023 — Wyndham Grand Residences Batumi Gonio. Riviera — Concreting of the 3rd floor floor slab has been carried out in the 1st half of Block A. In the 2nd half, the roof slab formwork is being installed. Excavation works are being carried out in Block B. In Block E, masonry of walls and partitions on the floors made of ceramic block is in progress.