fbpx

23.04.2024 — Wyndham Grand Residences Batumi Gonio. Family Club — Reinforcement and formwork installation of the 2nd stage of columns continues on the 5th floor of Block A. On the 1st floor, ceramic block wall masonry has been started. On the 2nd floor of Block B, reinforcement of columns is in progress.