23.07.2024 — Elite Family Residence — Work is underway to connect the tanks, waterproof the terraces, and install GKL frames at the storm drain frames and in the common areas. Installation of heating systems, as well as cold and hot water supply systems is in progress. The elevator portals are being laid with gas-silicate block.