27.05.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — Block A – the walls are being laid with ceramic block. Block B – reinforcement of vertical structures is in progress. Block C – excavation works are in progress. Infrastructure building – installation of formwork for the 2nd floor floor slab.