fbpx

28.03.2024 — Wyndham Grand Residences Batumi Gonio. Riviera — Laying of walls and internal partitions continues in Block A. Reinforcement of the 2nd stage of vertical structures has started in Block B. Earthworks are underway in Block C. Reinforcement of the foundation of the infrastructure building is underway.