28.04.2024 — Wyndham Grand Residences Batumi Gonio. Family Club — On the fifth floor of Block A, the floor slab formwork is being installed. On the first floor, the ceramic block walls continue to be laid. Reinforcement and installation of column formwork is underway in Block B.