Wyndham Grand Batumi Gonio. Aqua — 1. diamond drilling of engineering holes The marking and drilling is carried out, which is necessary for the installation of communications of the future hotel. 2. Mocap arrangement, 12th floor Allows visualization and verification of the design and materials of the hotel room. 3. Facade arrangement, 7th, 6th, 9th floors Works on facade arrangement on balconies. 4. Installation of stained glass windows, 2-5 floors. Preparation of boards for installation of stained glass windows. And installation of stained glass windows from 2 to 5 floors. 5. Installation of the ceiling frame on the balconies Provides strength and stability of the ceiling Also continue work on the installation of decorative boxes on the 8th floor, installation of gypsum plasterboard wall frame on the 3-6 floors.