Wyndham Grand Batumi Gonio. Aqua — 1. diamond drilling of engineering holes The marking and drilling is carried out, which is necessary for the installation of communications of the future hotel. 2. Mocap arrangement, 12th floor Allows visualization and verification of the design and materials of the hotel room. 3. Facade arrangement, 2-6 floors Works on facade arrangement on balconies. 4. Ceramoblock masonry, 4th, 19th-20th floors Checking all dimensions and compliance with technological norms. 5. Preparatory work for installation of stained glass windows Also works on installation of decorative columns on 6-7 floors, works on installation of gypsum cardboard frame of internal partitions on 2-4 floors.