fbpx

Wyndham Grand Batumi Gonio. Aqua — 1. Installation of stained glass structures, 4-5 floors Preparation of openings, installation of durable, environmentally resistant frames. 2. Installation of decorative boxes on balconies, 6,7 floors Design and creation of frame structure, secure fastening to ensure durability and safety. 3. Arrangement of mocap, 12th floor Creation of a sample finish, which allows us to assess the appearance of the future hotel room. 4. Plastering of openings and preparation for stained glass hydro/vapor barrier, 12th floor Installation of hydro and vapor barrier serves to protect stained glass windows from moisture and condensation, which helps to increase the durability of the structure. Anticorrosive works on the 1st floor, diamond drilling of engineering holes on the 8th-9th floors, works on elevator shaft coverings, works on installation of gypsum cardboard framework of internal partitions on the 12th floor, preparation of ceilings for installation of gypsum cardboard framework on the 5th floor.