fbpx

Wyndham Grand Batumi Gonio. Family Club. — Building A 1. Formwork is installed, concrete is poured and compacted. Upon completion of the concrete strength, the formwork is dismantled and the stained glass windows are installed. 2. Diamond drilling of engineering holes, 3rd floor Marking and drilling is carried out, which is necessary for the installation of communications of the future hotel. 3. Ceramoblock masonry, 4th floor on balconies Checking all dimensions and compliance with technological norms. Building B 1. Reinforcement of vertical structures, 5th floor Laying of reinforcement frames in accordance with the norms. Checking for compliance with the design and quality control of used materials