fbpx

Wyndham Grand Batumi Gonio. Riviera. — 1. Block B, Block C. Ceramoblock masonry Checking all dimensions and compliance with technological norms. 2. Drilling of engineering holes Marking and drilling is carried out, which is necessary for the installation of communications of the future hotel complex. 3. Block C. Pouring monolithic boards, on the 3rd floor Provides strength and durability of the structure. 4. Block C. Pouring monolithic belt on the parapet of the roof To provide rigidity and stability of the roof structure. 5. Block E. Pouring of columns on the terrace, on the 3rd floor Strengthens the frame of the building, creating support for the floors and ensuring safety and stability of the entire structure.