Wyndham Grand Batumi Gonio. Riviera. — 1. Laying of ceramic block. Block B on the 3rd floor, Block C on the 2nd floor, Block E on the 3rd floor on the terrace Laying ceramic blocks in compliance with technology. Ensuring the evenness and verticality of the walls. Checking all joints and corners for compliance with design requirements. 2. Block B. Pouring of monolithic sidewalls for stained glass windows, on the 3rd floor Includes preparation of the base, installation of formwork, uniform pouring of concrete and ensuring its hardening to create strong sidewalls. 3. Installation of formwork and stairway reinforcement framing To create molds for pouring concrete and ensuring the structure is solid. The formwork sets the desired shape and the reinforcing frame strengthens the stairways. 4. Block E. Pouring of columns on the terrace, on the 3rd floor