Wyndham Grand Batumi Gonio. Riviera. — The following key milestones are being accomplished during construction activities in Blocks A, B and C: 1. Block B, Block C. Ceramic block masonry The ceramic block masonry on the 3rd floor in Block B and on the 1st floor in Block C is performed. Including quality control to achieve design dimensions. 2. Dismantling and installation of stairway formwork. Dismantling and installation of staircase formwork includes careful removal of old formwork, design and installation of new framing system with panels, quality control and preparation for concrete pouring, ensuring strength and durability of the structure. 3. Block B. Fireplace masonry Fireplace masonry is carried out, ensuring conformity with the design and high quality of workmanship.