fbpx

Wyndham Grand Batumi Gonio. Aqua — Installation of stained glass windows continues at the site. Formwork installation, framing of balconies with reinforced concrete edges, installation of plasterboard framework of internal partitions (20th floor), as well as dusting of ceilings, installation of lift shaft covers, preparation for installation of lifts, geodesic works are in progress. In the mockup on the 3rd floor the installation of the frame and GKL partitions, installation of the ceiling frame, air-conditioning system, engineering networks continues. Balcony arrangement in the mockup on the 13th floor. Delivery of the corner to the object has been carried out.