Wyndham Grand Batumi Gonio. Family Club. — Building A 1. Formwork is installed, concrete is poured and compacted. Upon completion of the concrete strength, the formwork is dismantled and the stained glass windows are installed. 2. Diamond drilling of engineering holes, 2nd floor Marking and drilling is carried out, which is necessary for installation of communications of the future hotel. 3. Ceramoblock masonry, 3rd floor on balconies Checking all dimensions and compliance with technological norms. 4. Plastering of parapets, on the roof Building B 1. Reinforcement of vertical structures, 5th floor Laying of reinforcement frames in accordance with the norms. Checking for compliance with the project and quality control of materials used 2. Ceramoblock masonry, 3rd floor on balconies Checking all dimensions and compliance with technological norms.