Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Electrical installation, 17th floor.
— Plumbing installation, 3rd floor.
— Installation of ventilation system, 7th, 8th floor.

2. Installation of elevator shafts.
Installation of elevator equipment.

3. Arrangement of gypsum plasterboard frame.
Arrangement of the framework of partitions, sewing columns, sewing ceiling.

4. finishing works, 20th floor.
Laying tiles on the balconies.

5. Work on the roof of the building.
Waterproofing works on the roof.

6. Plastering works.
Plastering of balconies.

7. Masonry works, 10th floor.
Ceramoblock masonry.

8. Infrastructure building.
Waterproofing of the basement floor.