Wyndham Grand Batumi Gonio. Aqua
1. Facade works.
Plastering of the facade.
2. Installation of elevator shafts.
Installation of elevator equipment.
3. finishing works, 20th floor.
Laying tiles on the balconies.
4. Plastering works, 3, 5 floor.
Arrangement of decorative plaster.
5. Waterproofing works.
In units on the balconies of the 19th floor and on the roof of the building.
6. Arrangement of gypsum plasterboard frame.
Installation of partitions in the units.
7. Infrastructure building.
Installation of floor slab formwork on the 2nd floor.