Wyndham Grand Batumi Gonio. Aqua

1. Arrangement of engineering systems.
Electrical installation works.

2. Installation of elevator shafts.
— Installation of elevator equipment, installation of doors.
— Painting in elevator shafts.

3. finishing works, 20th floor.
Laying tiles on balconies, curbs and skirting boards.

4. Plastering works, 18th floor.
Decorative plastering.

5. Plasterboard frame installation works.
Arrangement of the ceiling frame on the balconies.

6. Works on waterproofing.
Works on the roof of the building.
7. Infrastructure building.
— Reinforcement of floor slab 2 floor.
— Waterproofing works.