Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
Electrical work: cable laying, clip installation, vent valve installation, 11th floor.

2. Installation of elevator shafts.
— Installation of elevator equipment, installation of motor.
— Installation of lighting in elevator shafts.

3. Plastering work.
Installation of decorative plaster.

4. Installation of plasterboard frame.
Installation of ceiling frames on balconies.

5. Waterproofing work.
Waterproofing of parapets.
6. Infrastructure building.
Reinforcement of vertical structures on the 3rd floor.