Wyndham Grand Batumi Gonio. Riviera.
1. Block A. Plastering work.
Plastering columns in the basement.
2. Block A. Facade work.
Plastering the ends of the facade.
3. Block E. Installation of engineering systems.
Electrical installation work, marking, fastening clips, cable routing.
4. Infrastructure building.
— Preparation of the roof for waterproofing work.
— Installation of window openings for glazing.