Wyndham Grand Batumi Gonio. Aqua.
1. Installation of engineering systems.
— Electrical work, 13th and 14th floors.
— Installation of fire extinguishing system, floors 6–20.
— Sealing of ventilation openings.
2. Plastering works.
Installation of decorative plaster on balconies.
3. Ceiling installation work, 14th-15th floors.
Installation of ceiling frames on balconies, covering of frames.
4. Facade work.
Plastering of the facade.
5. Infrastructure building.
Concreting of floor slabs, 5th floor.