Monthly Construction Report Wyndham Grand Batumi Gonio. Riviera September 2025

Monthly Construction Report Wyndham Grand Batumi Gonio. Riviera September 2025

Monthly Construction Report
Wyndham Grand Batumi Gonio. Riviera
September 2025

In September 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.

Block A
— Work has been completed on installing chimney flues above terrace level. The facade has been primed for the application of decorative plaster to the ends of the block.
— Work is underway on installing the plasterboard frame for internal partitions and covering them with plasterboard sheets.
— Work on the installation of hot and cold water supply, sewerage, and ventilation systems has been completed.
— Work is underway on electrical lighting, power supply, and the installation of a structured cabling system.
Blocks B and C
— Work is underway on the installation of welded waterproofing for the rear courtyards.
— Metal structures for chimney boxes are being manufactured for subsequent installation.
— Work is underway on the installation of hot and cold water supply, sewerage, and ventilation systems.
— Work is underway on electrical lighting, power supply, and installation of a structured cabling system.
Block E
— Work on the manufacture of engineering shaft covers has been completed.
— Work is underway on the installation of metal boxes for storm drainage and the covering of storm drainage boxes.

Infrastructure building
— Work on the installation of membrane waterproofing on the roof has been completed.
— Stained glass frames and double-glazed windows have been delivered.
— Work is underway on the installation of mineral wool facade insulation.