Get a Consultation

← All news

Monthly construction report

Monthly construction report

Monthly construction report
Wyndham Grand Batumi Gonio. Riviera
October 2025

In October 2025, work continued on the main areas of the Wyndham Grand Batumi Gonio complex construction sites: monolithic construction, facades, engineering networks, and interior finishing. Work was carried out simultaneously on several sites, which allowed us to maintain a high pace and steady progress towards the key stages of the project.

Block A
— Work has been completed on the installation of chimney boxes on all townhouses.
— Work is underway on the installation of upper waterproofing on the balconies of the townhouses.
— Storm sewer boxes have been manufactured.
— Work has begun on the installation of mats and pipes for underfloor heating.

Blocks B and C
— Hot and cold water supply, sewerage, and ventilation systems have been installed.
— Work has been completed on the manufacture of chimney boxes and engineering shaft umbrellas.

Block E
— Work is underway on the installation of plasterboard frames for internal partitions.
— Work has been completed on the manufacture and installation of chimney boxes.
— Work is underway on the sealing of storm sewer boxes.
— Facade work is underway to install mineral wool and plaster.

Infrastructure building
— Facade work has been completed to install mineral wool and reinforce it. Plastering work is underway.
— Work is underway to install plasterboard frames for internal partitions.