Wyndham Grand Batumi Gonio. Aqua

1. Installation of engineering systems.
— Electrical installation, 17th floor.
— Installation of ventilation system, 7.

2. Plasterboard frame installation.
Arrangement of the partition frame, column sealing, ceiling sealing.

3. finishing works, 20th floor.
Laying tiles on the balconies.

4. Plastering works.
Plastering balconies.

5. Arrangement of boards for the installation of stained glass.
Pouring curbs.

6. Works in the workshop.
Manufacturing of details.

7. Infrastructure building.
Reinforcement of walls of the 2nd floor.