On the floors the walls are being masoned with ceramic block. Lintels are being installed on the 6th construction (5th residential) floor.
Construction progress, complex updates and real estate investment news from Batumi
On the floors the walls are being masoned with ceramic block. Lintels are being installed on the 6th construction (5th residential) floor.
Block A: Concreting of the first stage of columns was carried out on the 3rd floor. Dismantling of the floor slab formwork continues on the 2nd floor. Block B…
Riviera — Block A: installation of the roof slab formwork is in progress Block B: excavation works are in progress Block E: walls and internal partition walls…
Aqua — Formwork installation of the floor slab of the 20th construction (19th hotel) floor is in progress. Ceramic block wall masonry is underway on the 13th…
Ceramic block masonry walls are laid on floors.
Riviera — On the 2nd and 3rd floor of block E works on laying of walls and internal partitions with ceramic block are in progress.
Ceramic block wall masonry continues on the 13th construction (12 hotel) floor.
Loading of building materials on the floors has been carried out. Laying of walls and internal partitions with ceramic block is in progress.
Block A The roof slab formwork is installed. Block B Excavation works are carried out. Block E Ceramic block walls and partition walls are being laid on the…
Aqua — Work continues on the installation of the formwork for the floor slab of the 20th construction (19th hotel) floor. Loading of equipment has been carried…
Block A: dismantling of the floor slab formwork for the 2nd floor. Block B: preparation for concreting of the foundation slab is underway.
On the 7th construction (6th residential) floor, the laying of walls with ceramic block continues.
Block A: preparations are underway for concreting of the 1st stage of the 3rd floor columns. Block B: formwork installation and reinforcement of the foundation…
Installation of roof slab formwork continues in Block A. Excavation works are in progress in Block B. In Block E, masonry walls and internal partitions are…
Aqua — The installation of formwork for the floor slab of the 20th construction (19th hotel) floor is underway, as well as the laying of walls with ceramic…
Laying of walls with ceramic block continues. Loading of building materials on the floors has been carried out.
Block A: Reinforcement and formwork installation of the 3rd floor columns is in progress. Block B: Reinforcement and formwork installation of the foundation…
Block A: Installation of roof slab formwork continues in the first half. Dismantling of the roof slab formwork started in the second half. Block B: Excavation…
Aqua — Installation of the floor slab formwork of the 20th construction (19th hotel) floor is in progress. On the 13th (12th) floor the walls are being laid…
Block A: installation of formwork and reinforcement of the 3rd floor columns is in progress. Block B: installation of formwork and reinforcement of the…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st