Aqua — Installation of formwork for columns of the 20th construction (19th hotel) floor continues. On 14 (13) and 15 (14) the walls are being laid with ceramic…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Installation of formwork for columns of the 20th construction (19th hotel) floor continues. On 14 (13) and 15 (14) the walls are being laid with ceramic…
Ceramic block masonry walls are being laid on the 6th construction (5 residential) and 7th (6) floors.
Family Club — On the 3rd floor of Block A, dismantling of column formwork and installation of floor slab formwork continues.
Riviera — Concreting of the roof slab is carried out in block A. Laying of walls and partitions with ceramic block continues in block E.
Aqua — The formwork for the columns of the 20th construction (19th hotel) floor is being assembled. Ceramic block walls are being laid on the 14th (13th) and…
Ceramic block masonry walls are installed on the 6th construction (5 residential) and 7th (6) floors.
In Block A, after concreting of the 2nd stage of columns, the dismantling of their formwork is underway, and the installation of formwork for the 3rd floor…
Riviera — Block A: reinforcement of the roof slab. Block E: laying of walls and internal partitions with ceramic block.
Aqua — On the 20th construction (19th hotel) floor the reinforcement of columns is in progress. On the 14th (13th) and 15th (14th) floors - wall masonry with…
Ceramic block masonry walls are being laid on the 6th construction (5 residential) and 7th (6) floors.
Family Club — Concreting of columns of the 2nd stage has been carried out on the 3rd floor of Block A. Preparation for concreting of the foundation slab is…
Riviera — Reinforcement of the roof slab continues in Block A. In Block E, the walls and partition walls are being laid with ceramic block.
Aqua — On the 20th construction (19th hotel) floor, columns are being marked out and the reinforcement frames of the columns are being prepared. On the 13th…
Ceramic block masonry walls are laid on floors.
Preparation for concreting of the foundation slab of Block B continues.
Excavation works continue in Block B. In Block E the walls are being laid with ceramic block.
Aqua — Reinforcement frames are being prepared for installation on the 20th construction (19th hotel) floor. On the 13 (12) and 14 (13) floors, the walls are…
The walls are being laid with ceramic block on the floors. Work on lintels is in progress.
Laying of walls and partitions in Block E is in progress. Land works are in progress.
The masonry walls on the 13th (12th) and 14th (13th) floors are under construction.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st