In Block A, installation of the formwork for the 2nd floor slab continues, reinforcement has started. Soil levelling and backfilling have been carried out.
Construction progress, complex updates and real estate investment news from Batumi
In Block A, installation of the formwork for the 2nd floor slab continues, reinforcement has started. Soil levelling and backfilling have been carried out.
Aqua — Installation of the formwork for the floor slab of the 17th construction (16th hotel) floor is in progress. On 6 (5), 7 (6) and 14 (13) the walls are…
On the 2nd building (1 residential), as well as on the 3rd (2) and 4th (3) floors, the walls are being laid with ceramic block. Ground planning is underway in…
Installation of the formwork for the floor slab of the 2nd floor of Block A, backfilling works and ballast leveling continue.
Riviera — In Block A, the floor slab formwork is being installed and thermal insulation of the underground part of the foundation is underway. In Block E…
Aqua — Installation of the formwork for the floor slab of the 17th construction (16th hotel) floor has started. Ceramic block wall masonry continues on the 6th…
Ceramic block wall masonry continues on 2 construction (1 residential), 3 (2), 4 (3) floors.
Aqua — On the 16th construction (15 hotel) after concreting the dismantling of the column formwork is in progress. On the 6 (5), 7(6), 14 (13) floors, the…
Family Club — Installation of formwork for the 2nd floor slab and installation of insulation on the underground part of the foundation is in progress…
Riviera — Installation of the floor slab formwork started in Block A and works on installation of insulation on the underground part of the foundation…
On building 2 (1 residential), as well as on 3 (2), 4 (3) the laying of walls with ceramic block is in progress.
In Block A, installation of the floor slab formwork continues. The insulation of the outer part of the basement wall is being installed.
Aqua — On the 16th construction (15 hotel) floor the concreting of columns has taken place. On 7 (6) the laying of walls with ceramic block continues. On 14…
Riviera — Formwork dismantling took place in Block A. Staircase reinforcement continues in Block E.
On building 2 (1 residential), as well as on 3 (2), 4 (3) the laying of walls with ceramic block is in progress.
In Block A, installation of the floor slab formwork continues. The insulation of the outer part of the basement wall is being installed.
Riviera — Concreting of columns has been completed in Block A and insulation is being installed. In Block E, the floor slab formwork is being assembled.
Aqua — On the 16th construction (15th hotel) floor the installation of column formwork is in progress. On 6(5) the ceramic block wall masonry continues, on 7(6)…
Installation of the floor slab formwork continues in Block A. Backfilling of soil was carried out at the place of insulation installation.
Riviera — Preparations for concreting of columns are underway in Block A. In Block E, welding and locksmithing work on the staircase formwork continues.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st