Work is underway to install a protective canopy.
Construction progress, complex updates and real estate investment news from Batumi
Work is underway to install a protective canopy.
Stage 3 of reinforcement of the 1st floor columns of Block A continues.
Riviera — Reinforcement of the 1st floor columns is going on in Block A. Reinforcement of the 3rd floor columns and installation of the staircase formwork is…
Aqua — On the 16th construction floor (15th hotel floor), geodetic works on column axes have been carried out. Reinforcement of the columns has started and…
Riviera — Column reinforcement continues on the 1st floor of Block A. On the 3rd floor of block E, column reinforcement and staircase formwork installation is…
Aqua — Concreting of the floor slab has been carried out on the 16th construction (15 hotel) floor. On 6 (5), the wall masonry with ceramic block continues.
Column formwork of Stage 2 is being dismantled after concreting in Block A. Reinforcement of columns continues.
Riviera — Reinforcement of the 1st floor columns continues in Block A. Reinforcement of the 3rd floor columns is being carried out in Block E. Staircase…
Aqua — On the 16th construction (15 hotel) floor reinforcement of the floor slab continues. On 6 (5), the walls are being laid with ceramic block.
Concreting of the second stage of the 1st floor columns and stairs took place in Block A.
This is the final pouring of the facility. Next, masonry walls will continue, communications, finishing and other works will begin. Other objects are only being…
On the 2nd construction (1 residential) floor, the laying of walls with ceramic block continues.
Installation of column formwork continues on the 1st floor of Block A.
Riviera — In Block A, reinforcement of the 1st floor columns is in progress. In Block E, reinforcement of the 3rd floor columns and installation of staircase…
Reinforcement of the floor slab continues on the 16th construction (15th hotel) floor.
Aqua — Work is underway to install the formwork for the floor slab of the 16th construction (15th hotel) floor. On the 6th (5th) floor the walls are being laid…
The laying of ceramic block walls on the 2nd (1st) floor is in progress.
Family Club — Dismantling of the formwork of the first part of the columns of the 1st floor of Block A.
Riviera — Column reinforcement continues on the 1st floor of Block A and on the 3rd floor of Block E. The reinforcement of the staircase in block E is also…
Reinforcement of the floor slab above the 7th construction (6th residential) floor is completed. Laying of ceramic block walls on the 2nd (1st) floor is in…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st