Block A - on the 3rd floor the walls are being laid with ceramic block. In Block C the floor slab formwork is being assembled. In Block E, fireplaces and…
Construction progress, complex updates and real estate investment news from Batumi
Block A - on the 3rd floor the walls are being laid with ceramic block. In Block C the floor slab formwork is being assembled. In Block E, fireplaces and…
Installation of profiles for GPB partitions is in progress.
Installation of cold and hot water supply systems, heating systems, engineering openings is in progress. Installation of the fire extinguishing system and…
Villas — The dismantling of formwork for the fence of the complex was carried out. Formwork installation, reinforcement and waterproofing of the foundation are…
Column reinforcement is underway on the 4th floor of Block B.
In block A on the 3rd floor, the laying of walls with ceramic block continues. In Block E, fireplaces are being built and staircases are being reinforced.
Balcony framing and installation of profiles for GKL partitions is in progress.
Utility penetrations and installation of cold and hot water systems continue.
The following types of works are performed: - construction of capital fencing of the complex - reinforcement of foundations - waterproofing of foundations…
Column reinforcement is underway on the 4th floor of Block B.
On the 3rd floor of block A the walls are being laid with ceramic block. Concreting of the floor slab has taken place in Block B. Fireplaces are being installed…
Aqua — Installation of profiles for installation of GKL partitions and balcony framing is in progress.
Installation of cold and hot water supply systems is in progress. Installation of engineering openings is in progress.
Foundation reinforcement and installation of capital fencing is underway.
In Block B, the reinforcement of the vertical structures is underway.
In block A the walls are being laid with ceramic block on the 2nd and 3rd floors. Dismantling of the staircase formwork continues in Block E.
Installation of hot and cold water supply systems continues. Installation of engineering openings has started.
Villas — Reinforcement of the foundation and installation of the complex's capital fence continues.
Reinforcement of the vertical structures continues in Block B.
Block A - on the 3rd floor the walls are being laid with ceramic block. Block B - installation of floor slab formwork. Block E - masonry of fireplaces and…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st