Villas — Work is underway on the fencing of the complex and reinforcing the foundations of the villas.
Construction progress, complex updates and real estate investment news from Batumi
Villas — Work is underway on the fencing of the complex and reinforcing the foundations of the villas.
In block A on the 2nd floor, the walls are being laid with ceramic block. On the 4th floor of Block B the reinforcement of columns is underway.
On the 3rd floor of Block A, the ceramic block walls continue to be laid. In Block C, the floor slab formwork is being assembled.
Installation of cold/hot water supply and heating systems is in progress. Engineering openings in floor slabs and framing under GPB in common areas are being…
The fencing of the complex and reinforcement of the foundation are in progress.
Block A - on the 2nd floor the walls are being laid with ceramic block. Block B - reinforcement of vertical structures is in progress.
Concreting of the floor slab has been carried out in the infrastructure building. In Block A, wall masonry with ceramic block continues on the 3rd floor. The…
Aqua — Installation of profiles for installation of GKL partitions continues on the 3rd construction (2 hotel) floor.
Installation of cold and hot water supply systems, construction of engineering holes and framework for storm water drainage is in progress.
Reinforcement of the foundations of the villas is carried out.
On the 2nd floor of block A the walls are being laid with ceramic block.
On the 3rd floor of Block A, wall masonry with ceramic block continues. The floor slab formwork is being assembled in block C. Staircase formwork is being…
Aqua — On the 3rd construction (2 hotel) floor the installation of profiles for GKL partitions continues.
Installation of cold and hot water supply and heating systems is in progress. Engineering openings in floor slabs, installation of drainage lines for air…
Fencing of the complex territory and reinforcement of the foundations are in progress.
In Block B, reinforcement of vertical structures on the 4th floor is underway.
Riviera — The following works are in progress: - in Block A - laying of ceramic block walls on the 3rd floor; - in Block E - installation of staircase formwork…
Installation of profiles for the installation of GKL partitions is in progress.
Cold/hot water supply and heating systems are being installed on the floors, engineering holes are being made in floor slabs, and drainage lines for air…
The fencing of the complex and reinforcement of the foundation is in progress.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st