13.06.2024 — Wyndham Grand Residences Batumi Gonio. Riviera

Block A - laying of walls with ceramic block on the 3rd floor. Block B - dismantling of floor slab formwork. Block C - installation of vertical structures…

13.06.2024 — Wyndham Grand Residences Batumi Gonio.

Aqua — Building materials are being loaded onto the floors. On the 7th construction (6th hotel) floor the monolithic framing of the balconies is under…

12.06.2024 — Elite Family Residence

Facade works, installation of warm floors, cold and hot water supply systems, storm water system, terrace construction are in progress.

12.06.2024 — Wyndham Grand Residences Batumi Gonio.

Family Club — On the 2nd floor of block A the walls are being laid with ceramic block. On the 3rd floor of block B - reinforcement of the floor slab.

12.06.2024 — Wyndham Grand Residences Batumi Gonio. Riviera

On the 3rd floor of block A the walls are being laid with ceramic block. In Block B, the floor slab formwork is being dismantled. In block C - installation of…

Georgia's GDP Continues to Grow in 2023

In June 2023, Georgia's GDP increased by 7.7%. The average growth rate for the first half of 2023 was 7.6%, according to the Georgian National Statistical…

New Premium Hotel From Wyndham Hotels & Resorts Opens in Greece

The world’s largest hotel network, Wyndham Hotels & Resorts, has unveiled its first European property under one of its two premium brands, Registry Collection…