03.06.2024 — Wyndham Grand Residences Batumi Gonio.

Aqua — On 7 construction (6 hotel) technological holes are being made. On 5 (4) monolithic sides of balcony framing are being installed.

02.06.2024 — Elite Family Residence

Facade works continue on the outside, while inside the walls are being plastered and hot and cold water supply systems are being installed.

02.06.2024 — Wyndham Grand Residences Batumi Gonio. Family Club

Block A - on the 2nd floor the walls are being laid with ceramic block.

02.06.2024 — Wyndham Grand Residences Batumi Gonio. Riviera

Block A - the walls are being laid with ceramic block on the 2nd floor. Block B - installation of column formwork and floor slab is in progress.

02.06.2024 — Wyndham Grand Residences Batumi Gonio.

Aqua — Installation of formwork, reinforcement and concreting of balcony framing boards is performed on the 5th construction (4 hotel) floor.

01.06.2024 — Elite Family Residence

Plastering works are underway on the floors, as well as installation of hot and cold water supply systems.

Georgia's GDP Continues to Grow in 2023

In June 2023, Georgia's GDP increased by 7.7%. The average growth rate for the first half of 2023 was 7.6%, according to the Georgian National Statistical…

New Premium Hotel From Wyndham Hotels & Resorts Opens in Greece

The world’s largest hotel network, Wyndham Hotels & Resorts, has unveiled its first European property under one of its two premium brands, Registry Collection…