21.05.2024 — Elite Family Residence

Facade and plastering works continue. Gas utilities are being connected on the floors and installations are being installed in the bathrooms.

21.05.2024 — Wyndham Grand Residences Batumi Gonio. Family Club

Block A - concreting of the roof slab has been carried out. Monolithic frame works in the block are completed. Wall masonry with ceramic block on the 1st floor…

21.05.2024 — Wyndham Grand Residences Batumi Gonio. Riviera

Block A - on the 2nd floor ceramic block wall masonry continues. Block B - reinforcement of the floor slab. Block C - excavation works. Infrastructure building…

21.05.2024 — Wyndham Grand Residences Batumi Gonio.

Aqua — On the 3rd construction (2 hotel) floor reinforcement and concreting of the monolithic sides of the balcony framing is carried out. Technological…

20.05.2024 — Elite Family Residence

Plastering, facade and roofing works are in progress. Installation of gas supply systems is in progress.

20.05.2024 — Wyndham Grand Residences Batumi Gonio.

Family Club — Installation of the roof slab formwork and ceramic block wall masonry continues in Block A. Column reinforcement is underway in Block B.

Georgia's GDP Continues to Grow in 2023

In June 2023, Georgia's GDP increased by 7.7%. The average growth rate for the first half of 2023 was 7.6%, according to the Georgian National Statistical…

New Premium Hotel From Wyndham Hotels & Resorts Opens in Greece

The world’s largest hotel network, Wyndham Hotels & Resorts, has unveiled its first European property under one of its two premium brands, Registry Collection…