Installation of stained glass windows continues on the 4th construction (3 residential) floor. On the floors works on protective packaging of stained glass…
Construction progress, complex updates and real estate investment news from Batumi
Installation of stained glass windows continues on the 4th construction (3 residential) floor. On the floors works on protective packaging of stained glass…
Family Club — Reinforcement of the 4th floor columns is underway in Block A. Reinforcement of the basement walls continues in Block B.
Riviera — Dismantling of the floor slab formwork is underway in Block A. In the 1st part of Block B the marking of the basement floor columns is underway, in…
Aqua — Reinforcement of vertical structures continues on the roof. On the 16th building (15th hotel) walls are being laid with ceramic block.
Riviera — Block A: dismantling of the floor slab formwork is in progress Block B: concreting of the foundation slab is underway Block E: ceramic block walls are…
Aqua — On the 16th construction (15th hotel) floor the masonry of walls with ceramic block continues, and on the roof the reinforcement of parapets and elevator…
Packing of stained glass windows in protective film is in progress. Loading of building materials on the floors has been carried out.
Family Club — Block A: reinforcement of columns is underway Block B: reinforcement of basement walls.
Installation and protective packaging of stained glass windows is in progress. Building materials for fireplaces are loaded.
Family Club — Column reinforcement continues on the 4th floor of Block A. Basement wall reinforcement is underway in Block B.
Riviera — The floor slab formwork is being dismantled in Block A. Reinforcement of the foundation slab is carried out in Block B. Ceramic block walls are being…
Aqua — Reinforcement of vertical structures continues on the roof. On the 16th construction (15th hotel) floor the walls are being laid with ceramic block.
On the floors, the installation and wrapping of the stained glass windows in protective film is underway.
Column marking has begun on the 4th floor of Block A.
Riviera — Block A - dismantling of the floor slab formwork Block B - reinforcement of the foundation slab Block E - laying of walls with ceramic block
Aqua — Dismantling of formwork has started and reinforcement of vertical structures on the roof is in progress. Ceramic block wall masonry has started on the…
Installation of the stained glass windows on the floors continues.
Reinforcement of the basement walls continues in Block B.
Riviera — Dismantling of the floor slab formwork is carried out in Block A. In Block B, reinforcement of the foundation slab is in progress. In Block E, the…
Aqua — Concreting of parapets and elevator shaft exits was carried out on the roof. On the 15th construction floor (14 hotel floors) the masonry of walls with…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st