Installation of stained glass windows continues on the 2nd construction (1 residential) floor.
Construction progress, complex updates and real estate investment news from Batumi
Installation of stained glass windows continues on the 2nd construction (1 residential) floor.
Family Club — Concreting of the floor slab of the 4th floor and staircases in Block A has been completed. Reinforcement of the basement walls in Block B is in…
Connection to the municipal water supply is in progress. Block A Dismantling of floor slab formwork in progress. Block B Reinforcement of the foundation slab is…
Ceramic block wall masonry continues on the 15th construction (14th hotel) floor. Reinforcement on the roof has been completed and installation of formwork for…
The installation of the stained glass windows is underway on the 2nd construction (1 residential) floor.
Block A - reinforcement of staircases Block B - reinforcement of basement walls.
Connection of the facility to the municipal water supply system has been started. Block A - dismantling of the floor slab formwork Block B - reinforcement of…
Marking and reinforcement of vertical structures is carried out on the roof.
The installation of stained glass windows continues on Building 4 (3 residential).
Staircase reinforcement is in Block A. Basement walls reinforcement is in Block B.
Riviera — Dismantling of the floor slab formwork continues in Block A. In Block B, reinforcement of the foundation slab is underway. On the 1st floor of block…
Aqua — Reinforcement of vertical structures continues on the roof slab. On the 15th construction (14 hotel) the walls are being masoned with ceramic block.
The installation of the stained glass windows continues on the 4th construction (3rd residential) floor.
Family Club — Block A - reinforcement of the 4th floor floor slab and staircases Block B - reinforcement of the basement walls.
Riviera — Block A - dismantling of the floor slab formwork Block B - excavation and reinforcement of the foundation slab Block E - laying of walls with ceramic…
Aqua — The vertical structures have been marked out on the roof slab and reinforcement has been started.
The installation of the stained glass windows is underway on the 4th construction (3rd residential) floor.
Block A: Reinforcement of the floor slab is in progress. Block B: Reinforcement of the basement walls is in progress.
Block B: reinforcement of the foundation slab is in progress. Block E: works on laying walls with ceramic block on the 1st floor are in progress.
Concreting of the roof slab has been carried out.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st