Reinforcement of the floor slab of the 4th floor continues in Block A. Reinforcement of the basement walls is underway in Block B.
Construction progress, complex updates and real estate investment news from Batumi
Reinforcement of the floor slab of the 4th floor continues in Block A. Reinforcement of the basement walls is underway in Block B.
In Block A, dismantling of the floor slab formwork is in progress. In the first part of Block B, the reinforcement of the foundation slab continues. In Block E…
Aqua — Reinforcement of the roof slab over the 20th construction (19th hotel) floor is in progress. Wall masonry with ceramic block on the 15th (14th) floor is…
Installation of stained glass windows on the 3rd construction (2nd residential) floor is underway.
Installation of stained glass windows on the 3rd construction (2nd residential) floor is underway.
Family Club — Reinforcement of the floor slab of the 4th floor continues in Block A. Reinforcement of the basement walls is underway in Block B.
Dismantling of the floor slab formwork is underway in Block A. In the first part of Block B, reinforcement of the foundation slab is in progress, in the second…
Aqua — Reinforcement of the roof slab over the 20th construction (19th hotel) floor is in progress. Wall masonry with ceramic block on the 15th (14th) floor is…
The installation of stained glass windows on the 3rd construction (2 residential) floor is underway.
Family Club — Reinforcement of the floor slab of the 4th floor continues in Block A. In Block B - reinforcement of the basement walls.
Riviera — Block A: dismantling of the floor slab formwork Block B: reinforcement of the foundation slab in the 1st part, excavation works in the 2nd part Block…
Aqua — Reinforcement of the roof slab continues above the 20th construction (19th hotel) floor. Wall masonry with ceramic block is in progress on the 15th…
The installation of the stained glass windows continues on the 3rd construction (2nd residential) floor.
Reinforcement of the floor slab of the 4th floor of Block A continues.
Dismantling of the floor slab formwork is underway in Block A. Excavation works are being carried out in Block B. Reinforcement of the 2nd stage of the…
Aqua — Reinforcement of the roof slab is being carried out above the 20th construction (19th hotel) floor. On the 14th (13th) and 15th (14th) floors, wall…
The installation of the stained glass windows is underway on the 3rd construction (2nd residential) floor.
Family Club — Reinforcement of the floor slab is underway on the 4th floor of Block A. Column reinforcement continues on the foundation slab of Block B.
Riviera — Dismantling of the floor slab formwork is underway in Block A. Excavation works are in progress in Block B. Ceramic block wall masonry continues in…
Aqua — The installation of roof slab formwork and ceramic block walls on the 14th (13th) and 15th (14th) floors continue.
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st