Aqua — Reinforcement of vertical structures continues on the 19th construction (18 hotel) floor. Ceramic block wall masonry is carried out on the 11th (10) and…
Construction progress, complex updates and real estate investment news from Batumi
Aqua — Reinforcement of vertical structures continues on the 19th construction (18 hotel) floor. Ceramic block wall masonry is carried out on the 11th (10) and…
On the 6th construction (5 residential) and 7th (6) floors the walls are being laid with ceramic block. Preparations for masonry of the roof parapet have…
Family Club — Reinforcement of the 3rd floor slab continues in Block A. Reinforcement of the foundation slab has started in Block B.
Column formwork installation works are underway on the 3rd floor of Block A. Excavation works continue in Block B. In Block E Building materials are loaded on…
Aqua — Column reinforcement continues on the 19th construction (18 hotel) floor. On 11 (10) and 12 (11) the walls are being laid with ceramic block.
Ceramic block wall masonry continues on the 6th construction (5 residential) and 7th (6) floors.
Block A: Reinforcement of the floor slab of the 3rd floor is in progress. Block B: Concreting of the foundation preparation is in progress.
Block A: In the first half on the 3rd floor, work is being carried out on the installation of vertical structures. Block B: Excavation works are in progress…
Aqua — On the 19th construction floor (18 hotel floors) the marking and reinforcement of columns is in progress. On the 11th (10th) floor, work continues on the…
Ceramic block wall masonry continues on the 6th construction (5 residential) and 7th (6) floors.
Work continues on the reinforcement of the floor slab on the 3rd floor of Block A.
In Block A on the 3rd floor, work continues on the installation of vertical structures. Lighting is being installed. Ground works are being carried out in Block…
Continuation of works on reinforcement of vertical structures on the 19th construction (18 hotel) floor. On the 11th (10) and 12th (11) floors, wall masonry…
In Block A on the 3rd floor, work continues on the installation of vertical structures. Lighting is being installed. Ground works are being carried out in Block…
Marking and reinforcement of vertical structures on the 19th construction (18 hotel) floor is in progress. On the 11th (10) floor, wall masonry with ceramic…
Ceramic block wall masonry continues on the 6th construction (5 residential) and 7th (6) floors.
Reinforcement of the floor slab continues on the 3rd floor of Block A. In Block B the excavation works are completed.
On the 6th construction (5 residential) and 7th (6) floors, the walls are being masoned with ceramic block.
Reinforcement of the floor slab continues on the 3rd floor of Block A. The excavation is being completed in Block B.
In Block A on the 3rd floor, work has started on the installation of vertical structures. Lighting installation is in progress In Block B, ground works are in…
Nothing found
Leave a request and we will pick a property for your budget and goal
Get a consultationGet personal advice from a specialist in branded real estate Wyndham Grand
Thank you for the application!
Within 5 minutes, our expert will contact you and tell you in detail about everything personally.
Get a consultation and gifts with purchases until December 31st